Work progress - Mid of May 2010



Lot 1 – 3 : Formwork to 1st floor beam & slab in Progress
Read More...

Apr 17, 2010

retaining wall p1



Inspection before casting








Read More...

Apr 16, 2010

retaining wall



Construction of RC Wall near lot 1 & 3











Read More...

PDA test



Dynamic Piles testing on 200mm x 200mm rc pile using the Pile Driving Analyser (PDA)










Data will be analyse using computer CAPWAP analysis
(to stimulate pile / soil model and load settlement behavior of the tested pile)


Read More...

setting out



Setting out by License Surveyor as per drawing before Piling Work carried out.







Read More...

Mar 31, 2010

work progress - end of march 2010









Read More...

Mar 12, 2010

bukit aman



congratulation to all parties...

Read More...

Feb 25, 2010

syabas pipe



manhole at site (2/12/09)







encik zaki from syabas visit the site on 9/2/10






pressure test by syabas, pressure result = 5 bar (24/2/10)





chlorine test done; Syabas confirmed that pipe still active



Read More...

load test


1st maintain load test for 200mm x 200mm RC pile (start 1030-24/2/10 ---> finish 1030-26/2/10)










Read More...

Feb 24, 2010

1st pile


piling work opening ceremony by mr chairman on 10/2/10





Read More...

Jan 19, 2010

latest boundary survey

Today Jurukur Teguh (owner's surveyor)confirmed that neighbouring lot (PT 33302)wall fencing encroached into our site 658mm, 484mm and 283mm.

Previously contractor's surveyor (Jurukur Ehsan) reported that the lot PT33302 wall fencing into our site about 600mm. The survey was done based on latest CP drawing

view near lot 9


view near lot 21 and lot 27

Read More...