Lot 1 – 3 : Formwork to 1st floor beam & slab in Progress
May 20, 2010
Apr 17, 2010
Apr 16, 2010
PDA test
Dynamic Piles testing on 200mm x 200mm rc pile using the Pile Driving Analyser (PDA)
Data will be analyse using computer CAPWAP analysis
(to stimulate pile / soil model and load settlement behavior of the tested pile)