Welcome to Perunding Bersatu's Blog at Bukit Jelutong Site, Shah Alam

May 20, 2010

Work progress - Mid of May 2010



Lot 1 – 3 : Formwork to 1st floor beam & slab in Progress
Read More...

Apr 17, 2010

retaining wall p1



Inspection before casting








Read More...

Apr 16, 2010

retaining wall



Construction of RC Wall near lot 1 & 3











Read More...

PDA test



Dynamic Piles testing on 200mm x 200mm rc pile using the Pile Driving Analyser (PDA)










Data will be analyse using computer CAPWAP analysis
(to stimulate pile / soil model and load settlement behavior of the tested pile)


Read More...

setting out



Setting out by License Surveyor as per drawing before Piling Work carried out.







Read More...